| Sr. No. | Particulars | Details/Status |
|---|---|---|
| 1 | Project Name | Four Laning of Gundugolanu – Devarapalli- Kovvuru Section from Km 15+320 (Existing Km 15.700) to Km .85+204 (Existing Km 81.400)(Design Length=69.884 Km) in the state of Andhra Pradesh on Hybrid Annuity Mode |
| 2 | NH No. (New/old) | NH-16/ SH-107 |
| 3 | Scheme/Phase | Bharatmala Pariyojna |
| 4 | Mode of Execution | HAM |
| 5 | No. of Lanes/Configuration | Four Lane |
| 6 | Bid Project Cost | 1827 Cr. |
| 7 | No. Of Bypasses(Name of Town, Length) | 06 Nos. (Bhimadole-5.280 Km, Dubacherla- 4.510 Km, Km, Nallajerla-3.350 km, Ananthapalli- 3.090 Km, Yernagudem-3.120 Km, Devarapalli- 25.314 Km) |
| 8 | No. Of Minor Bridges | New MNB -16 Nos., Reconstruction& New Construction of MNB -04 Nos., Repair of Existing MNB & Construction of new MNB -01 Nos., Widening of Existing Minor Bridge -04 Nos., |
| 9 | No. of Culverts | RCC Box Culverts- Reconstruction of Box Culvert-7 Nos. New Culverts-106 Nos. Widening /Repairing of Existing Culverts -8nos. Culverts across the Cross road-1 Nos. |
| 10 | No. of Elevated Viaducts | 19 Nos. |
| 11 | No. of Major Bridges | 09 Nos. |
| 12 | No. of ROB | 01 Nos. |
| 13 | No. of Underpasses | 11 Nos. |
| 14 | Toll Plaza | 01 Nos. |
| 15 | Concessionaire Name | GR Gundugolanu Devarapalli Highway Private Limited |
| 16 | Date of Letter of award(LOA) | 13.03.2018 |
| 17 | Appointed Date | 22.10.2018 |
| 18 | Construction Period (in Days) | 910 Days |
| 19 | Schedule Completion Date | 910 days from Appointed Date |
| 20 | Operation & Maintenance Period | 15 Years from the Commercial Operation Date |
| 21 | Independent Engineer | M/S MSV International Inc. in association with ARMENGE Engineering and Management Consultants Pvt. Ltd. |
| 22 | Authority Name | National Highways Authority of India, PIU-Rajahmundry |
| 23 | Independent Engineer Mobilization Date | 01.11.2018 |